YTB Plumbing were engaged to complete the civil connections for the new Infinity Tower on Surf Parade Broadbeach.
The water connection was a 25 meter open cut trench across Surf Parade complete with a double stacked water meter assembly and with an after hours night shift for the cut in connection, with all footpath / road reinstatement also a part of our scope.
The sewer connection was a 2.5 meter deep Wang clamp connection in the road with a maintenance shaft install in the verge and then take a 150mm line into the boundary.
And the stormwater connection was to build and construct a 1050 mm manhole over an existing Council main complete with a 375mm road crossing across George Street and then build a new lip in line Gully pit and take a new RCP line into the boundary. All Road reinstatement was part of our scope also.
Client Testimonial
"As a company that’s been established on the Gold Coast for 15 plus years, it’s always been hard to find a level of service that Pete from YTB gives with the civil connections. We’ve been using YTB for nearly 5 years now and couldn’t recommend the team enough. From Low-risk connections to intricate OPW sewer diversions on main road corridors, the team at YTB seem to get it done without any hassles or issues. YTB’s relationship with all third-party entities on all civil connections are very close and well respected which is defiantly a reflection of the high level of professionalism and attention to detail on every job they have completed for us whether it be big or small. As YTB is a family owned and operated company it’s not uncommon to call the office to be redirected to peter the owner who will be onsite with his team and still take the time to discuss future works. It’s this reason YTB is our only choice when it comes to civil connections."
Jesse Backholm
Construction Supervisor